Research & Development Buildings

As of week ending 7/24/10 (remediation of the East Wing), 

  • The asbestos removal is complete from the interior surfaces.
  • The PCB-Lead based paint has been removed from all the brick and plaster interior surfaces. 
  • The north half of the East Wing's first floor had 1/2 inch of concrete scarified, high pressure washed and vacuumed in order to remove the PCB contaminated flooring.
  • The clean trades construction contractor was chosen, Couture Construction.
  • Construction of the new Visitor's Center starts Monday on the East Wing, south room.

Photos from clean up and more photos here!



Photos of R&D clean up start! (6/24/10)


     
     
 
     